SL.No. Name of work & Location Name of Division Estimated Cost Rs.inLacs Tendered Cost Rs.in Lacs Quantity Executed (Lacs CUM) Date of work Order Stipulated Period of Completion Actual Period of Completion Remarks
1 3 4 5 6 7 9 10 11 12
1 GNSS - Excavation of GNSS Flood Flow Canal from Owk Reservoir to Gandikota Reservoir including construction of CM & CD work from km 16.500 to km 34.800/32.520 in Kurnool and Kadapa Districts Package - 48 Irrigation & CAD PW Department E.P.C System 7855.90 E.P.C System 02.03.2005 24 Months 24 Months Completed
2 GNSS - Excavation of GNSS Flood Flow Canal from Owk Reservoir to Gandikota Reservoir including construction of CM & CD work from km 34.800 to km 52.875/52.184 in Kadapa District Package - 49 Irrigation & CAD PW Department E.P.C System 7365.80 E.P.C System 02.03.2005 24 Months 24 Months Completed
3 Earth work Excavation & F.E from Km 20.00 to Km 21.00 of FFC from SRSP, Andhra Pradesh. E.E, FFC Division - 2, Metpally, Andhra Pradesh 624.00 348.58 9.40 03.03.2004 21.03.2005 21.05.2004 Completed
4 Earth work Excavation from Km 14.00 to Km 15.00 of FFC from SRSP, Andhra Pradesh. E.E, FFC Division - 1, Metpally, Andhra Pradesh 339.00 167.62 3.50 09.03.2004 08.03.2005 20.11.2004 Completed